The rains have been trying to keep me from working on this kiln build.
Keeping the water out of the flooring has been my challenge as I try to get the sides and top on.
Not making the progress that I would like to me making. I need more time in the week and less other stuff needing to be done.
As I previously posted I have a 6 mil sheet down on top of the foam insulation, then the plywood flooring but water from rain likes to pool and my concern is that I will get infiltration. Thus I have another layer of 6 mil on top of the plywood and then a poly tarp on top of that.
Here I have at least gotten two of the phase 1 sides up but need to get the third up and get rafters and roofing on to stop the rain issue.
Not real happy with how far it is up in the air, but will have to live with it until I get it moved when we get the new place built and moved to.